CONNECT Hamilton is literally taking shape as the walls are going up on the first level of the building.

After a period of less visible progress, we are happy to be back on track and seeing progress each day.

The first floor framing should be mostly complete by the end of the week.

The second floor slabs will be delivered and placed August 7, with second floor framing following soon after.

We are actively working with city contractors to complete necessary road, sewer and utility upgrades on Upper Mount Albion Road for the fall, as we will be relying on those services to maintain our schedule.

CONNECT CEO John Sherwood was on site this week and flew a drone over the property. (Video footage to come.) John says he is happy to see things progressing on site and to witness the walls going up.

Left to right – Joe, the foreman for the siteworks dirt and foundations, John, and Tom, our site superintendent.